2025 Feb 7 update
The "back" (east) side of the fire station features the entry to the pull-through engine bays.
The team at Hyder Construction reported that our new Station 10 in Silverthorne is looking not far from the final product after a preliminary cleanup inside the building earlier this week, along with the completion of solar panels, snow fence, gutters and siding and stone on the outside.
West entrance
South facade
Next week, crews will be finishing up boiler/furnace start up, installing bathroom and backsplash tile, hanging the doors, sealing the interior concrete and installing gutter heat trace. We are on track (and on budget) to have the place up and running this spring, and the excitement is apparent!
Even the trash enclosure was designed to match the building and be inconspicuous.
Yep, as with any modern commercial building, we've got fire sprinklers
Solar panels on the south-facing roof aspect
These hollow metal interior doors are primed for painting.